note: this schedule could change depending on how long things actually take to finish, and if weather causes problems…but optimistically, the schedule below is the plan
updated Shed Construction Schedule:
(Hours being something like 8am – 6pm)
Present until March 14 — gathering materials, buy, find, load, unload, etc
——
Saturday March 7 — dug footing
Sunday March 8 — rain
Monday March 9 –rain
——-
Saturday March 14 — build stone foundation
Tuesday March 17 — finish foundation
Wednesday March 18 — let foundation dry, build the door buck and roof plate
Thursday March 19 — ‘raise’ the walls and set roof plate on top, compress, haul in clay!, start pony wall and roof
Wednesday March 25 — 2nd layer plaster
——-
Next weeks — letting plaster dry, pour/lay floor — finishing floor, other odds and ends
jana, i have a truck that can be used if you want. it is a 3/4 ton, so it can handle rock weight with no issue.